Haussman Construction Company was selected by the Building Committee
of the University Reformed Church to perform the addition to their
existing church using Construction Management for project delivery.
The project included a 9,000 square foot addition, and a construction
cost of approximately $1,000,000. This project was completed costing
the owner no more than originally budgeted.
This project included the addition of an office area at the front
of the building while also adding a two-story classroom addition
to the rear. Remodeling portions of the existing structure is also
included in the scope of the project. One of the difficulties overcome
at University Reformed Church was the need to remain in operation
while the construction engulfed the building.
Haussman Construction Company was selected as a construction manager
and was employed to work hand in hand with an architect to control
cost of the structure. The design was analyzed and manipulated by
Haussman Construction Company in order to bring the project down
from an original construction cost of $2,600,000 to the building
committees budget of $1,000,000.The structure is a exterior masonry
load bearing wall system with structural steel interior support
and roof framing. This structure presented a number of difficulties
including very limited site access and building clearances due to
the presence of vegetation as well as property limitations. Haussman
Construction Company worked within these limits to deliver a quality
final product.